While the vertical leg should be placed 1 4 1 2 away from the fascia.
Proper installation of roof drip edge.
Make sure to support the long end of the cut if you let it fall after cutting it will bend down and kink the drip edge.
If it doesn t pull the drip edge out slightly from under the shingles.
Slide the corner tight to the fascia.
Make sure the outer edge extends over the gutter.
You may need to nail through the starter strip into the drip edge.
Apply a continuous bead of cement along the top of the drip edge then press down on the shingle.
Place a nail at one end then the other.
The drip edge should be nailed centered in the top surface every 8 to 10 inches.
Secure the drip edge with roofing cement.
Slightly open the hemmed edge to slide this piece over top of the installed piece on the eave.
How to install a drip edge.
Align the leading bottom edge of the first piece on the gable rake with the front edge of the drip edge installed on the eave.
It can be done.
How to install drip edge flashing to a new roof.
Slip the wide flat flange of the material all the way under the first course of roof shingles as illustrated.
Once free slide the drip edge out and discard.
On the gable rake install drip edge starting at the bottom and working up.
Gently lift up the shingles on the edge of the roof and locate the nails holding the existing drip edge onto.
Make sure the corner is tight and that the bottom edge is tight to the fascia before nailing off the drip edge.
No cutting is needed for this piece.
The above figure shows the correct application of the drip edge.
At the rake the drip edge is installed over the underlay.
At the eaves the drip edge should be installed before the eave protection membrane.
Use a flat pry bar and hammer to pry the nails out of the drip edge gently.